Strawberry River Restoration Phase III
Strawberry River Restoration Phase III
Project Summary
Location Summary:
Strawberry River segment from Doe Knoll to Willow Creek
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/25/2007 |
Comment Period | 10/25/2007 |
Decision | 03/2008 (Estimated) |
Implementation | 06/2008 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Heber-Kamas Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Wildlife, Fish, Rare Plants; Watershed Management
Project Activity:
Species Habitat Improvements; Species Population Enhancements
Current Status:
Completed
Project Decision Information
Strawberry River Fish Habitat Phase III
Decision Signed Date: 03/06/2008
Legal Notice Date: 03/09/2008
Forests:
Uinta-Wasatch-Cache National Forest
Districts:
Heber-Kamas Ranger District
States:
Utah
Counties:
Wasatch
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Nathan Berg
2460 South Highway 40
Heber City, UT 84032
435-654-7227
nathanberg@fs.fed.us
Last Updated: 12/11/2009