Logan City Dewitt Springs Fiber Optic Line
The Logan Ranger District proposes to authorize two new utility poles to allow the City of Logan to install a fiber optic line that would run from Third Dam along the Logan River to its facility at Dewitt Springs.
Project Summary
Location Summary:
Near Third Dam along the Logan River.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/10/2013 |
Decision | 03/2014 (Estimated) |
Implementation | 04/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Logan Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Logan City Dewitt Springs Fiber Optic Line Project Decision Memo
Decision Signed Date: 03/17/2014
Forests:
Uinta-Wasatch-Cache National Forest
Districts:
Logan Ranger District
States:
Utah
Counties:
Cache
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ronald Vance
1500 East Highway 89
Logan, UT 84321
435-755-3628
rvance@fs.fed.us
Last Updated: 9/22/2014