Millville Peak Road Realignment
Proposal to realign 700 linear feet of FSR 20168 at milepost 5.17 on a stable slope to circumvent the unstable slump on the existing road prism. Abandoned road alignment will be obliterated.
Project Summary
Location Summary:
The project is located 5.17 miles east from the Forest boundary on the Millville Peak Road, FSR 20168.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/08/2021 |
Decision | 06/2021 (Estimated) |
Implementation | 07/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (24), 36 Cfr 220.6(E)(24)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Logan Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Decommissioning; Road Improvements/Construction
Current Status:
Completed
Project Decision Information
Millville Peak Road Realignment Decision Memo
Decision Signed Date: 06/17/2021
Forests:
Uinta-Wasatch-Cache National Forest
Districts:
Logan Ranger District
States:
Utah
Counties:
Cache
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ryan Stone
1500 East Highway 89
Logan, UT 84321
801-999-2138
rlstone@fs.fed.us
Last Updated: 6/21/2021