Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/17/2022 |
| Comment Period | 05/17/2022 |
| Objection Period Start | 05/2022 (Estimated) |
| Decision | 07/2022 (Estimated) |
| Implementation | 07/2022 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Heber-Kamas Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Vegetation Management (Other Than Forest Products)
Project Activity:
Road Maintenance; Timber Sales (Salvage)
Current Status:
Completed
Project Decision Information
North Heber Sale Additions - Determination of NEPA Adequacy
Decision Signed Date: 07/05/2022
Forests:
Uinta-Wasatch-Cache National Forest
Districts:
Heber-Kamas Ranger District
States:
Utah
Counties:
Wasatch
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Scott Frost
2460 South Highway 40
Heber City, UT 84032
541-573-4385
scott.frost@usda.gov
Last Updated: 7/5/2022