Laguna Water System Improvement
Installation of a new electrical drop and service, water and control line distribution to a new reservoir site, the installation of a new 100,000 gallon reservoir and water distribution line extension to connect to the existing Laguna water system.
Project Summary
Current Status:
Completed
Location Summary:
Mount Laguna Recreation Area
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/19/2013 |
| Comment Period | 05/09/2014 |
| Decision | 03/2015 (Estimated) |
| Implementation | 03/2015 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Descanso Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Facility Management
Project Activity:
Facility Improvements/Construction; Facility Maintenance
Project Decision Information
Laguna Water System Improvement
Decision Signed Date: 03/05/2015
Forests:
Cleveland National Forest
Districts:
Descanso Ranger District
States:
California
Counties:
San Diego
Legal Land Description:
T15S, R5E Sections 13, 14, 15, 22, 23, and 24
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Noelle Graham
3348 Alpine Boulevard
Alpine, CA 91901
858-674-2990
ngraham01@fs.fed.us
Last Updated: 3/9/2015