Santiago Peak Building 10 Generator
Approve construction of improvements needed to operate a generator in Santiago Peak, Building 10. Improvements include a concrete pad with walls, under 50 feet of buried propane line, fence relocation and building modifications.
Project Summary
Current Status:
Completed
Location Summary:
On top of Santiago Peak, along North Main Divide Road on the Trabuco Ranger District.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 08/28/2017 |
| Decision | 01/2018 (Estimated) |
| Implementation | 04/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Trabuco Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Santiago Peak Communications Facility 10 Generator Project
Decision Signed Date: 01/19/2018
Forests:
Cleveland National Forest
Districts:
Trabuco Ranger District
States:
California
Counties:
Orange; Riverside
Legal Land Description:
T5S, R6W, S29
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Amy Reid
1147 East Sixth Street
Corona, CA 92879
858-6742919
areid@fs.fed.us
Last Updated: 4/23/2018