Southern California Edison Company Master Permit Renewal
Approve continued operation, maintenance and use of existing distribution and transmission powerlines and infrastructure for Southern California Edison located within designated corridors on the Cleveland National Forest.
Project Summary
Location Summary:
Multiple powerlines across the Trabuco Ranger District and the very north end of the Palomar Ranger District (see map).
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/12/2018 |
Decision | 02/2019 (Estimated) |
Implementation | 02/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Trabuco Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Southern California Edison Company Master Permit Renewal
Decision Signed Date: 02/15/2019
Forests:
Cleveland National Forest
Districts:
Trabuco Ranger District
States:
California
Counties:
Orange; Riverside
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Joseph Raffaele
1147 East Sixth Street
Corona, CA 92879
858-674-2961
josepharaffaele@fs.fed.us
Last Updated: 3/26/2019