Control Silver Peak Project
Southern California Edison is proposing to update and reconfigure approximately 61 linear miles of two existing 55 kilovolt subtransmission lines originally designed and built in the 1930s. BLM is lead agency. Full description: https://bit.ly/44zSlg
Project Summary
Location Summary:
Silver and Wyman Canyons on the Inyo National Forest.
Project Milestones:
Milestone | Date |
---|---|
NOI in Federal Register | 12/29/2023 |
DEIS NOA in Federal Register | 05/2025 (Estimated) |
FEIS NOA in Federal Register | 02/2026 (Estimated) |
Objection Period Start | 11/2025 (Estimated) |
Decision | 02/2026 (Estimated) |
Implementation | 04/2026 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
Inyo National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission
Current Status:
On Hold
Forests:
Inyo National Forest
Districts:
White Mountain Ranger District
States:
California
Counties:
Inyo; Mono
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Nathan Sill
351 Pacu Lane
Bishop, CA 93514
626-574-5328
nathan.sill@usda.gov
Last Updated: 12/11/2024