Southern California Edison Company Master Permit Renewal
Approve continued operation, maintenance and use of existing distribution and transmission powerlines and infrastructure for Southern California Edison located within designated corridors on the Inyo National Forest
Project Summary
Location Summary:
Across the Inyo National Forest, outside of Wilderness.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/15/2018 |
Decision | 02/2019 (Estimated) |
Implementation | 04/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Inyo National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Southern California Edison Company Master Permit Renewal
Decision Signed Date: 02/15/2019
Forests:
Inyo National Forest
Districts:
Inyo National Forest All Units
States:
California
Counties:
Inyo; Mono
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Spencer Bleadorn
351 Pacu Lane
Bishop, CA 93514
603-536-1315
sbleadorn@fs.fed.us
Last Updated: 3/27/2019