DOJ Tower Replacement at Tassajera Peak Communications Site
The US Department of Justice (DOJ) proposes to replace their existing 20' tower with a new 40' tower on an approximately 8' x 8' concrete pad within the existing footprint of the communications site, and enclosed by a new 22' x 28' security fence.
Project Summary
Location Summary:
Approximately 6 miles west of Santa Margarita, CA in San Luis Obispo County
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 08/06/2020 |
| Decision | 09/2024 (Estimated) |
| Implementation | 12/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Santa Lucia Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
DOJ Tower Replacement at Tassajera Peak Communications Site
Decision Signed Date: 09/12/2024
Forests:
Los Padres National Forest
Districts:
Santa Lucia Ranger District
States:
California
Counties:
San Luis Obispo
Legal Land Description:
T29S, R12E, Section 20, Mt. Diablo Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
David Betz
1616 Carlotti Drive
Santa Maria, CA 93454
530-841-6131
david.betz@usda.gov
Last Updated: 9/12/2024