38. Chiloquin Dam Removal Staging Area Special Use Permit Request
The US Bureau of Reclamation has requested an SUP to clear an area adjacent to the south side of the dam and access to each side of the dam for equipment use and storage.
Project Summary
Current Status:
Completed
Location Summary:
South of Chiloquin High School at Chiloquin Dam location
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/22/2006 |
| Decision | 10/2006 (Estimated) |
| Implementation | 04/2007 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Chiloquin Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Chiloquin Dam Removal Staging Area Project
Decision Signed Date: 10/17/2006
Forests:
Fremont-Winema National Forest
Districts:
Chiloquin Ranger District
States:
Oregon
Counties:
Klamath
Legal Land Description:
T35S, R7E, Sec 3, SE 1/4 WM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kevin Moore
38500 Highway 97 North
Chiloquin, OR 97624
541-783-4039
krmoore@fs.fed.us
Last Updated: 4/4/2012