Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/01/2002 |
| Comment Period | 05/13/2004 |
| Decision | 07/2004 (Estimated) |
| Implementation | 10/2004 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Fremont-Winema National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Hickey Reservoir Special Use Permit
Decision Signed Date: 07/01/2004
Legal Notice Date: 07/01/2004
Forests:
Fremont-Winema National Forest
Districts:
Lakeview Ranger District
States:
Oregon
Counties:
Lake
Legal Land Description:
T39S, R22E Sec 17 NW1/4NW1/4 and Sec 18 NE1/4NE1/4
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Catherine Callaghan
1301 South G Street
Lakeview, OR 97630
541-947-6326
ccallaghan@fs.fed.us
Last Updated: 8/13/2004