2008 Range Allotment Improvements - Water Developments
Map 2. Development of 2 different water sources for improved allotment management and water protection. A spring will be developed with a spring-box, piping, trough construction and spring fencing. At another site, a water tank will be replaced.
Project Summary
Current Status:
Completed
Location Summary:
Bennet Flat Allotment (spring development) and Antelope Allotment (water tank replacement)
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/28/2008 |
| Decision | 09/2008 (Estimated) |
| Implementation | 09/2008 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (9), 36 Cfr 220.6(E)(9)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Paisley Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Grazing Management
Project Activity:
Grazing Allotment Management; Grazing Structural Improvements
Project Decision Information
2008 Range Water Improvement Projects
Decision Signed Date: 09/24/2008
Forests:
Fremont-Winema National Forest
Districts:
Paisley Ranger District; Silver Lake Ranger District
States:
Oregon
Counties:
Lake
Legal Land Description:
T33S, R17E, section 7 (spring develop.) and T28S, R12E, section 33 (tank replacement)
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Katie Blazer
Highway 31
Paisley, OR 97636
541-943-3114
kblazer@fs.fed.us
Last Updated: 9/25/2008