Revised Tomahawk Project
This is a 249 acre portion of the original Tomahawk Project that was enjoined by an order signed 11/25/08. This project will continue work in remaining units 1, 5, 6, 9, 10, 11 & 12 which pose a threat to the health of the forest.
Project Summary
Current Status:
Completed
Location Summary:
The project areas lie south of Hwy 140, east of Lake of the Woods.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/23/2008 |
| Comment Period | 01/30/2009 |
| Decision | 03/2009 (Estimated) |
| Implementation | 06/2009 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (14), 36 Cfr 220.6(E)(14)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Klamath Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Vegetation Management (Other Than Forest Products)
Project Activity:
Forest Vegetation Improvements
Project Decision Information
Revised Tomahawk Project
Decision Signed Date: 03/11/2009
Legal Notice Date: 03/13/2009
Revised Tomahawk Project
Decision Signed Date: 03/11/2009
Legal Notice Date: 03/19/2009
Forests:
Fremont-Winema National Forest
Districts:
Klamath Ranger District
States:
Oregon
Counties:
Klamath
Legal Land Description:
T36S R5E Sections 24; T36S R6E Sections 18, 19, 20, 21 W.M.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Steven Mooney
2819 Dahlia Street
Klamath Falls, OR 97601
541-783-4029
smooney@fs.fed.us