Bonneville Power Administration (BPA) Access Road Improvement
The proposed project would issue a road use permit with BPA to authorize road reconstruction maintenance on NFDR Roads 2901-013 and 2901-019 on the Silver Lake Ranger District to ensure that the BPA communications relay facility remains accessible.
Project Summary
Location Summary:
Township 30 South, Range 16 East, Sections 9 and 10, Willamette Meridian.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/02/2021 |
Decision | 04/2021 (Estimated) |
Implementation | 04/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Silver Lake Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Improvements/Construction
Current Status:
Cancelled
Forests:
Fremont-Winema National Forest
Districts:
Silver Lake Ranger District
States:
Oregon
Counties:
Lake
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ashley Philbeck
Highway 31
Silver Lake, OR 97638
541-947-6340
ashley.philbeck@usda.gov
Last Updated: 6/3/2023