Spring Creek Road Project
Spring Creek Road is a small timber sale planned to treat the Lobert stands remaining between Hill IRTC and the 242 fire.I am proposing to extend vegetation treatment to this small lodgepole stand, following the same PDCs and BMPs outlined in Lobert.
Project Summary
Current Status:
Completed
Location Summary:
Near Spring Creek Campground and Hwy 97, along the 400 road.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/26/2022 |
| Decision | 08/2022 (Estimated) |
| Implementation | 10/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (12), 36 Cfr 220.6(E)(12)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Chiloquin Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Forest Products
Project Activity:
Timber Sales (Green)
Project Decision Information
Spring Creek Road Project
Decision Signed Date: 08/25/2022
Forests:
Fremont-Winema National Forest
Districts:
Chiloquin Ranger District
States:
Oregon
Counties:
Klamath
Legal Land Description:
T. 33 S., R. 7 E., Sec 33
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Guillermo Sereno
38500 Highway 97 North
Chiloquin, OR 97624
541-783-4061
guillermo.sereno@usda.gov
Last Updated: 10/11/2022