BPA-Lapine-Chiloquin Priority Pole Project
BPA has identified roads that require maintenance to ensure safe access to the LAPI-CHIL-1 transmission facilities. The road maintenance will allow BPA to also perform wood pole replacements that need to be completed along the transmission line.
Project Summary
Location Summary:
Project area is located approximately one and a half miles west of the Chemult Ranger District.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/24/2023 |
| Decision | 06/2024 (Estimated) |
| Implementation | 08/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (23), 36 Cfr 220.6(E)(23)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Chemult Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management; Road Management
Project Activity:
Special Use Authorizations; Road Maintenance
Current Status:
In Progress
Forests:
Fremont-Winema National Forest
Districts:
Chemult Ranger District
States:
Oregon
Counties:
Klamath
Legal Land Description:
T. 27 S., R. 8 E., Sec. 7, 18, and 19.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Guillermo Sereno
P.O. Box 150
Chemult, OR 97731
5417834061
guillermo.sereno@usda.gov
Last Updated: 12/8/2023