Bootleg Fire 2024 Bridge Repairs
Four Road Bridge repairs are needed from Bootleg Fire. The bridges are located in the Paisley, Silver Lake, and Bly Ranger Districts: the Pike%u2019s Crossing Bridge, Sycan Marsh Bridge, Sycan Spring Bridge, and the North Fork Sprague Bridge.
Project Summary
Current Status:
Completed
Location Summary:
Pike's Crossing Bridge: T33S, R16E, Sec. 27; Sycan Marsh Bridge: T32S, R14E, Sec. 22; Sycan Spring Bridge: T31S, R14E, Sec. 9; North Fork Sprague Bridge: T35S, R14E, Sec. 36
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/30/2024 |
| Decision | 06/2024 (Estimated) |
| Implementation | 07/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (23), 36 Cfr 220.6(E)(23)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Paisley Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Maintenance
Project Decision Information
Bootleg Fire 2024 Bridge Repairs
Decision Signed Date: 06/12/2024
Forests:
Fremont-Winema National Forest
Districts:
Bly Ranger District; Paisley Ranger District; Silver Lake Ranger District
States:
Oregon
Counties:
Klamath; Lake
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Parker Hill
Highway 31
Paisley, OR 97636
000-000-0000
Parker.Hill@usda.gov
Last Updated: 6/12/2024