Switchback Restoration Project (Bly Mountain Phase Two)
The Chiloquin Ranger District aims to improve resource conditions and increase forest resilience to insect and disease infestation in a portion of the Bly Mountain planning area.
Project Summary
Current Status:
Completed
Location Summary:
The project area is approximately six mile southwest of the town of Sprague River, OR.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/11/2025 |
| Decision | 10/2025 (Estimated) |
| Implementation | 04/2027 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.3 (5)
Special Authority:
Hfra Title Vi: Insect And Disease Projects
Lead Management Unit:
Chiloquin Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Forest Products; Vegetation Management (Other Than Forest Products); Fuels Management
Project Activity:
Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green)
Project Decision Information
Switchback Restoration Project (Bly Mountain Phase Two)
Decision Signed Date: 10/06/2025
Forests:
Fremont-Winema National Forest
Districts:
Chiloquin Ranger District
States:
Oregon
Counties:
Klamath
Legal Land Description:
T36S, R9E, Sec. 23-27, 25 and 36; T36S, R10E, Sec 31
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Guillermo Sereno
38500 Highway 97 North
Chiloquin, OR 97624
541-883-3448
guillermo.sereno@usda.gov
Last Updated: 10/7/2025