Cascade Creek Salvage
This project will commercially salvage 56 acres of matrix land within the Cascade Creek Fire where a majority of the trees have died or will die soon. Ground based logging and 0.3 miles of temporary road are included.
Project Summary
Current Status:
Completed
Location Summary:
Cascade Creek
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/28/2013 |
| Comment Period | 06/20/2013 |
| Decision | 08/2013 (Estimated) |
| Implementation | 09/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (13), 36 Cfr 220.6(E)(13)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Gifford Pinchot National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Forest Products
Project Activity:
Timber Sales (Salvage)
Project Decision Information
Cascade Creek Salvage Decision Memo
Decision Signed Date: 08/08/2013
Legal Notice Date: 08/08/2013
Forests:
Gifford Pinchot National Forest
Districts:
Mt Adams Ranger District
States:
Washington
Counties:
Skamania
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Erin Black
987 McClellan Road Vancouver
Vancouver, WA 98661
541-352-6002 ext. 634
ekblack@fs.fed.us
Last Updated: 8/9/2013