Martin Gap Restoration Thinning Project
Project Summary
Location Summary:
The project area encompasses approximately 3,834 acres within the Upper White River watershed, adjacent to the Clearwater Roadless Area and Muckleshoot Federal Corporation land.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 9/1/2025 |
| Decision | 2/2026 (Estimated) |
| Implementation | 6/2027 (Estimated) |
Expected Analysis Type:
Categorical Exclusion
Lead Management Unit:
Snoqualmie Ranger District
Project Purpose:
Vegetation management (other than forest products); Wildlife, fish, rare plants
Current Status:
Developing Proposal
Project Decision Information
Expected Decision Date: 2/2026 (Estimated)
States:
Washington
Counties:
Pierce
Levi Rose
c/o Snoqualmie Ranger District
902 SE North Bend Way, Bldg 1
North Bend, Washington 98045
564-669-4687
levi.rose@dnr.wa.gov
Last Updated: 12/23/2025