2013 Middle Fork Irrigation District Projects
Four projects would be completed by MFID within the permit area: (1) Clear Branch Dam Parapet Wall Refurbishment; (2) Right-of-Way Bushing; (3) Sediment Basin Cleaning; and, (4) Wood Placement Below Clear Branch Dam.
Project Summary
Location Summary:
Laurenace Lake and Settling Pond approximately seven miles SW of Parkdale, Oregon
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/19/2013 |
Comment Period | 02/19/2013 |
Decision | 06/2013 (Estimated) |
Implementation | 07/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hood River Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Developed Site Management; Hydropower; Facility Maintenance
Current Status:
Completed
Project Decision Information
Middle Fork Irrigation District 2013 Maintenance Projects
Decision Signed Date: 06/06/2013
Legal Notice Date: 06/12/2013
Forests:
Mt. Hood National Forest
Districts:
Hood River Ranger District
States:
Oregon
Counties:
Hood River
Legal Land Description:
T1S, R9E, Sections 23, 26, 27, and 28
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Darcy Saiget
6780 Highway 35
Parkdale, OR 97041
541-352-1222
darcysaiget@fs.fed.us
Last Updated: 6/17/2013