Timberline Pucci Night Lighting and Snowmaking
The project would involve trenching to install three new night lighting extensions and one new snowmaking power extension within the Special Use Permit Area of Timberline.
Project Summary
Location Summary:
Timberline Special Use Permit Area
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/31/2025 |
| Decision | 03/2025 (Estimated) |
| Implementation | 06/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (22), 36 Cfr 220.6(E)(22)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Zigzag Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Facility Improvements/Construction; Special Use Authorizations
Current Status:
Completed
Project Decision Information
Timberline Pucci Night Lighting and Buzz Cut Snowmaking Power Extensions
Decision Signed Date: 03/05/2025
Forests:
Mt. Hood National Forest
Districts:
Zigzag Ranger District
States:
Oregon
Counties:
Clackamas
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Allison Sweeney
70220 E. Highway 26
Zigzag, OR 97049
208-677-8303
allison.sweeney@usda.gov
Last Updated: 3/6/2025