Portland General Electric (PGE) Undergrounding Summit 13 Distribution Powerline
As part of PGE's Wildfire Mitigation Plan, there is a need to minimize wildland fire risk associated with utilities in the National Forest. Therefore, this project would underground approximately 5 miles of existing powerline.
Project Summary
Location Summary:
Community of Government Camp and Timberline Lodge
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/01/2025 |
| Decision | 06/2025 (Estimated) |
| Implementation | 08/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Zigzag Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Current Status:
Completed
Project Decision Information
Portland General Electric (PGE) Undergrounding Summit 13 Distribution Powerline
Decision Signed Date: 06/18/2025
Forests:
Mt. Hood National Forest
Districts:
Zigzag Ranger District
States:
Oregon
Counties:
Clackamas
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jay Martin
70220 E. Highway 26
Zigzag, OR 97049
503-668-1476
Jay.Martin3@usda.gov
Last Updated: 6/26/2025