Portland General Electric Bethel-Round Butte Transmission Line Project
Authorize a special use permit for Portland General Electric to continue to operate electrical tranmission lines across National Forest lands on the Willamette, Mt. Hood, and Ochoco National Forests.
Project Summary
Location Summary:
The Bethel-Round Butte transmission line crosses lands on the Willamette, Mt. Hood, and Ochoco NFs beginning on the Warm Springs Reservation.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/03/2008 |
Comment Period | 11/07/2008 |
Decision | 12/2008 (Estimated) |
Implementation | 01/2009 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Detroit Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
PGE Special Use Permit
Decision Signed Date: 12/15/2008
Forests:
Mt. Hood National Forest; Ochoco National Forest; Willamette National Forest
Districts:
Clackamas River Ranger District; Prineville Ranger District; Detroit Ranger District
States:
Oregon
Counties:
Clackamas; Marion
Legal Land Description:
T9S, R5,6,7,8E, multiple sections
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Rich Hatfield
HC73, Box 320
Mil City, OR 97360
503-854-4219
hatfield@fs.fed.us
Last Updated: 12/16/2008