Governor Davis Placer Mine Plan of Operations
Placer mining Plan of Operations for exploration and sampling.
Project Summary
Current Status:
Completed
Location Summary:
Along Josephine Creek, about 3.5 miles from Josephine Campground
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/06/2011 |
| Comment Period | 10/10/2012 |
| Decision | 09/2013 (Estimated) |
| Implementation | 10/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Wild Rivers Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Project Decision Information
Governor Davis Mining Decision Memo
Decision Signed Date: 09/11/2013
Legal Notice Date: 09/15/2013
Forests:
Rogue River-Siskiyou National Forest
Districts:
Wild Rivers Ranger District
States:
Oregon
Counties:
Josephine
Legal Land Description:
T. 38 S., R. 8 W., Sections 30 and 31
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Robert Shoemaker
2164 N.E. Spaldning Avenue
Grants Pass, OR 97526
541-471-6708
rshoemaker@fs.fed.us
Last Updated: 9/16/2013