J. Herbert Stone Nursery Solar Array
As part of a grant from Department of Energy the Forest Service proposes to construct a 500.5-kilowatt solar array, covering approx. 1.2 acres, at the nursery site. The life expectancy of the array exceeds 20 years.
Project Summary
Current Status:
Completed
Location Summary:
J. Herbert Stone Nursery
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/12/2016 |
| Comment Period | 11/01/2016 |
| Objection Period Start | 12/15/2016 |
| Decision | 02/2017 (Estimated) |
| Implementation | 03/2017 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Rogue River-Siskiyou National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Facility Management
Project Activity:
Facility Improvements/Construction
Project Decision Information
J. Herbert Stone Nursery Solar Array
Decision Signed Date: 02/06/2017
Forests:
Rogue River-Siskiyou National Forest
Districts:
J. Herbert Stone Nursery
States:
Oregon
Counties:
Jackson
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Sitka Pence
3040 Biddle Road
Medford, OR 97504
541-426-5689
sitkapence@fs.fed.us
Last Updated: 12/10/2019