Bowen WUI Project
The intent of this project is to reduce fuels, and increase resiliency of the stands through commercial, and mechanical thinning. Activity fuels may be either piled, or loped and scattered.
Project Summary
Location Summary:
Located in the Big Butte Springs Watershed, about 5 miles east of Butte Falls, Oregon.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/30/2018 |
Decision | 12/2020 (Estimated) |
Implementation | 12/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (12), 36 Cfr 220.6(E)(12)
Special Authority:
Not Applicable / Other
Lead Management Unit:
High Cascades Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Fuels Management
Project Activity:
Fuel Treatments (Non-Activity Fuels)
Current Status:
Cancelled
Forests:
Rogue River-Siskiyou National Forest
Districts:
High Cascades Ranger District
States:
Oregon
Counties:
Jackson
Legal Land Description:
T35S, R3E, Sec 29 and 30 FS Lands west of Willow Lake
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Anne Trapanese
47201 Highway 62
Prospect, OR 97536-9724
541-365-7097
atrapanese@fs.fed.us
Last Updated: 9/21/2020