Tollgate Fuels Reduction Project
The project seeks to conduct fuels reduction activities within the Tollgate Wildland Urban Interface (WUI). Due to an error in the legal notice (published in East Oregonian on 12/28/2012), the project's comment period has been extended to March 15, 2013.
Project Summary
Location Summary:
Located within Tollgate Wildland Urban Interface, established in Umatilla County CWPP
Project Milestones:
| Milestone | Date |
|---|---|
| NOI in Federal Register | 10/19/2010 |
| DEIS NOA in Federal Register | 12/31/2012 |
| FEIS NOA in Federal Register | 12/13/2013 |
| Objection Period Start | 12/13/2013 |
| Decision | 06/2014 (Estimated) |
| Implementation | 07/2014 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Lead Management Unit:
Walla Walla Ranger District
Notice and Comment Regulation:
218
Project Purpose:
Fuels Management
Project Activity:
Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements
Current Status:
Completed
Forests:
Umatilla National Forest
Districts:
Walla Walla Ranger District
States:
Oregon
Counties:
Umatilla
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Holly Hutchinson
1415 West Rose St.
Walla Walla, WA 99362
208-347-0325
hollyahutchinson@fs.fed.us
Last Updated: 9/11/2015