East Nottely Watershed Project
The purpose of this project is to improve forest health in over-crowded and fire-excluded stands to lower the risk of insect and disease infestation (particularly southern pine beetle) and reduce susceptibility to damaging wildfire.
Project Summary
Current Status:
Completed
Location Summary:
Union County, Georgia
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/30/2010 |
| Comment Period | 07/30/2010 |
| Decision | 10/2011 (Estimated) |
| Implementation | 02/2012 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Blueridge Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Watershed Management
Project Activity:
Watershed Improvements
Project Decision Information
East Nottely Watershed Project
Decision Signed Date: 10/31/2011
Forests:
Chattahoochee-Oconee National Forests
Districts:
Blueridge Ranger District
States:
Georgia
Counties:
Union
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Alice Brown
1881 Highway 515
Blairsville, GA 30514
803-276-4810
alicebrown@fs.fed.us
Last Updated: 7/17/2019