Locust Stake OHV Trail Mtce. & Reconstruction Project
Locust Stake OHV Tail Mtce. & Reconstuction Project
Project Summary
Current Status:
Cancelled
Location Summary:
Stephens County, Georgia
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/24/2014 |
| Comment Period | 03/21/2014 |
| Objection Period Start | 03/2017 (Estimated) |
| Decision | 04/2017 (Estimated) |
| Implementation | 02/2018 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Chattooga River Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Forests:
Chattahoochee-Oconee National Forests
Districts:
Chattooga River Ranger District
States:
Georgia
Counties:
Stephens
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jill Davis Belanger
809 Highway 441S
Clayton, GA 30525
706-754-6221
jdavisbelanger@fs.fed.us
Last Updated: 8/9/2018