Watauga River Regional Water Authority
Road Easement to access water intake station near Wilbur Lake
Project Summary
Location Summary:
Road Easement near Wilbur Dam on Watauga Lake
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/01/2009 |
Comment Period | 04/01/2009 |
Decision | 11/2010 (Estimated) |
Implementation | 01/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Watauga Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Watauga River Regional Water Authority Access Road and Pipeline Project
Decision Signed Date: 11/17/2010
Forests:
Cherokee National Forest
Districts:
Watauga Ranger District
States:
Tennessee
Counties:
Carter
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Frank Lege
P.O. Box 400
Unicoi, TN 37692
423-735-1500
flege@fs.fed.us
Last Updated: 2/15/2011