Volunteer Electric Cooperative proposes burying a powerline in a roadbed that crosses 100 ft. of National Forest System lands. The line will be 7200 volts and buried in a trench 6 inches wide by 36 inches deep.
Project Summary
Location Summary:
Reliance
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/23/2010 |
Decision | 12/2010 (Estimated) |
Implementation | 02/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Tellico Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
VEC Buried Powerline
Decision Signed Date: 12/16/2010
Forests:
Cherokee National Forest
Districts:
Ocoee - Hiwassee Ranger District
States:
Tennessee
Counties:
Polk
Legal Land Description:
T1 R3E Section 2
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Alex Faught
250 Ranger Station Rd
Tellico Plains, TN 37385
423-338-3313
afaught@fs.fed.us
Last Updated: 10/2/2015