Pond Mountain II Project
Vegetation management and wildlife activities in vicinity of Little Pond Mountain
Project Summary
Location Summary:
Compartments 29 - 34; Carter County, TN
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/20/2010 |
| Comment Period | 01/17/2012 |
| Decision | 06/2012 (Estimated) |
| Implementation | 08/2012 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Watauga Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Wildlife, Fish, Rare Plants; Watershed Management; Vegetation Management (Other Than Forest Products); Road Management; Forest Products
Project Activity:
Road Decommissioning; Forest Vegetation Improvements; Species Habitat Improvements; Species Population Enhancements; Road Maintenance; Road Improvements/Construction; Timber Sales (Green)
Current Status:
Completed
Project Decision Information
Pond Mountain II Project
Decision Signed Date: 06/05/2012
Forests:
Cherokee National Forest
Districts:
Watauga Ranger District
States:
Tennessee
Counties:
Carter
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jeff Chynoweth
P.O. Box 400
Unicoi, TN 37692
423-638-4109
jjchynoweth@fs.fed.us
Last Updated: 5/17/2017