Cowbell Hollow Horse Trail Relocation Project (Trail #24).
This project proposes constructing approx. 330 ft. of new trail to relocate the trail away from an existing spring.
Project Summary
Location Summary:
Trail 24
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/29/2016 |
Decision | 04/2017 (Estimated) |
Decision | 08/2016 (Estimated) |
Implementation | 04/2017 (Estimated) |
Implementation | 04/2017 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Unaka Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Current Status:
Completed
Project Decision Information
Cowbell Hollow Horse Trail Relocation Project (Trail #24).
Decision Signed Date: 04/24/2017
Forests:
Cherokee National Forest
Districts:
Unaka Ranger District
States:
Tennessee
Counties:
Greene
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Lynn DiFiore
4900 Asheville Hwy.
Greenville, TN 37743
423-735-1561
ldifiore@fs.fed.us
Last Updated: 7/18/2017