NEON's Geotechnical Study
NEON proposes to conduct a geotechnical study in LBJ's Unit 75 in order to gather information for a future project.
Project Summary
Current Status:
Completed
Location Summary:
LBJ Unit 75, approximately 10 miles north of Decatur, Texas.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/18/2013 |
| Comment Period | 07/13/2013 |
| Decision | 08/2013 (Estimated) |
| Implementation | 09/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Caddo - Lyndon B. Johnson National Grasslands
Notice and Comment Regulation:
215
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Project Decision Information
NEON's Geotechnical Study Decision Memo
Decision Signed Date: 08/19/2013
Legal Notice Date: 08/21/2013
Forests:
National Forests In Texas
Districts:
Caddo - Lyndon B. Johnson National Grasslands
States:
Texas
Counties:
Wise
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Amanda Bataineh
1400 US Hwy 81/287
Decatur, TX 76234
940-627-5475
abataineh@fs.fed.us
Last Updated: 9/5/2013