Aspen Well #802 SUPO Amendment
Proposal to amend the surface use plan of operation and install two utility poles and anchors to supply electric power to the Aspen Operating Company's Alvord South Caddo Conglomerate Unit #802 well site.
Project Summary
Location Summary:
Unit 41
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/26/2010 |
| Decision | 06/2011 (Estimated) |
| Implementation | 08/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (3), 36 Cfr 220.6(D)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Caddo - Lyndon B. Johnson National Grasslands
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
Utility Development by Aspen Operating Company, LLC
Decision Signed Date: 06/15/2011
Forests:
National Forests In Texas
Districts:
Caddo - Lyndon B. Johnson National Grasslands
States:
Texas
Counties:
Wise
Legal Land Description:
Unit 41 is located about 4 miles southeast of Alvord, Texas.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
David Weldon
1400 US Hwy 81/287
Decatur, TX 76234
940-627-5475
dweldon@fs.fed.us
Last Updated: 7/19/2011