Compartment 112 Longleaf Pine Restoration Project
Create and improve wildlife habitat by restoring and sustaining a functioning longleaf pine community in Compartment 112.
Project Summary
Location Summary:
Compartment 112, Sam Hosuton National Forest
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/25/2014 |
Comment Period | 07/19/2014 |
Objection Period Start | 08/29/2014 |
Decision | 06/2015 (Estimated) |
Implementation | 07/2015 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Sam Houston Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Wildlife, Fish, Rare Plants; Vegetation Management (Other Than Forest Products); Fuels Management
Project Activity:
Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Noxious Weed Treatments
Current Status:
Completed
Project Decision Information
DN/FONSI Compartment 112 Longleaf Pine Restoration Project
Decision Signed Date: 06/23/2015
Forests:
National Forests In Texas
Districts:
Sam Houston Ranger District
States:
Texas
Counties:
San Jacinto
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Daniel Jauregui
394 FM 1375 West
New Waverly, TX 77358
936-344-6205
djauregui@fs.fed.us
Last Updated: 9/11/2015