Highway 94 Power Line Relocation
Houston County Electric Cooperative (HCEC) Proposes to install a 3-phase above ground power line partially within State Highway 94 right-of-way.
Project Summary
Location Summary:
Trinity County Texas, State Highway 94 right-of-way, north side, within Davy Crockett National Forest Compartment 110. Also 0.6 miles north of State Highway 94 and FM Road 2262 intersection.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 09/23/2019 |
Decision | 03/2020 (Estimated) |
Implementation | 04/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Davy Crockett Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission
Current Status:
Completed
Project Decision Information
Highway 94 Power Line Relocation
Decision Signed Date: 03/18/2020
Forests:
National Forests In Texas
Districts:
Davy Crockett Ranger District
States:
Texas
Counties:
Trinity
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Bobi Stiles
18551 State Highway 7 East
Kennard, TX 75847
936-553-3449
bobi.stiles@usda.gov
Last Updated: 3/24/2020