Utility ROW from Osburn Rd to FM149
Designating a 18,527 ft by 10 ft utility corridor. A 12-inch diameter natural gas pipeline wwould be installed by boring under an existing smaller diameter pipeline.
Project Summary
Location Summary:
Compartments 29-32 along Tracts J-1-III and J-1-IV
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/19/2024 |
Decision | 01/2025 (Estimated) |
Implementation | 01/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
National Forests In Texas All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Utility ROW from Osburn Rd to FM149
Decision Signed Date: 01/15/2025
Forests:
National Forests In Texas
Districts:
Sam Houston Ranger District
States:
Texas
Counties:
Montgomery
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Edwin Davis
2221 N. Raguet St.
Lufkin, TX 75904
936-337-7057
edwin.d.davis@usda.gov