Pine Bear
Proposed activities include vegetation, wildlife habitat, non-native invasive plant species, transportation, and soil and water management. Oil and gas development is ongoing within the project area.
Project Summary
Location Summary:
Warrants 1464, 1465, 1776, 1778, 1783, 1799, 1831, 1858, 1863, 2032, 2033, 2034, 3655, 3656, 3657, 3776, Highland Twnshp; Warrants 3252, 4846, Jones Twnshp; and Warrant 4846, Ridgway Twnshp
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/16/2010 |
Comment Period | 06/01/2011 |
Decision | 01/2012 (Estimated) |
Implementation | 05/2012 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Marienville Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Vegetation Management (Other Than Forest Products); Watershed Management; Road Management; Forest Products
Project Activity:
Road Decommissioning; Forest Vegetation Improvements; Noxious Weed Treatments; Road Improvements/Construction; Timber Sales (Green); Watershed Improvements
Current Status:
Completed
Project Decision Information
Pine Bear
Decision Signed Date: 01/11/2012
Legal Notice Date: 01/18/2012
Forests:
Allegheny National Forest
Districts:
Marienville Ranger District
States:
Pennsylvania
Counties:
Elk
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kevin Treese
131 Smokey Lane
Marienville, PA 16239
814-927-5759
ktreese@fs.fed.us
Last Updated: 5/16/2019