The Branch Stream Improvement Project
The project involves hardening the toeslope and stabilize streambank for slope stability of Forest Road 145 near its intersection with Forest Road 127 by constructing a multi-faceted log complex and installing other instream structures.
Project Summary
Location Summary:
Warrrant 5109, Kingsley Township
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/14/2013 |
| Comment Period | 04/17/2013 |
| Decision | 08/2013 (Estimated) |
| Implementation | 11/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Marienville Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Road Management; Watershed Management
Project Activity:
Road Maintenance; Watershed Improvements
Current Status:
Completed
Project Decision Information
The Branch Stream Improvement Project
Decision Signed Date: 08/01/2013
Legal Notice Date: 08/05/2013
Forests:
Allegheny National Forest
Districts:
Marienville Ranger District
States:
Pennsylvania
Counties:
Forest
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kevin Treese
131 Smokey Lane
Marienville, PA 16239
814-927-5759
ktreese@fs.fed.us
Last Updated: 8/5/2013