Brown Run Road, S.R. 2010 Bridge Replacement Pipeline Relocation Project
The Forest Service is reviewing a request from PAPCO Inc. and Gas & Oil Management Associates, Inc. for amendments to their existing special use permits to relocate three natural gas pipelines within the Robert Falconer Warrant, Mead Township, Warren
Project Summary
Location Summary:
Brown Run Road, S.R. 2010
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/08/2018 |
| Decision | 10/2018 (Estimated) |
| Implementation | 10/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Allegheny National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Facility Improvements/Construction; Natural Gas
Current Status:
Completed
Project Decision Information
Brown Run Road, S.R. 2010 Bridge Replacement Pipeline Relocation Project
Decision Signed Date: 10/09/2018
Forests:
Allegheny National Forest
Districts:
Bradford Ranger District
States:
Pennsylvania
Counties:
Warren
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ava Turnquist
4 Farm Colony Drive
Warren, PA 16365
814-363-6086
aturnquist@fs.fed.us