Whirlpool Parking Lot Enhancement
Expand the parking Area of the current Whirlpool Access Site to meet the increased use at the site. This action will also decrease the runoff to the Au Sable River.
Project Summary
Location Summary:
Located due east of the Lumberman's Monument Visitor Center and Foote Dam Pond on the River Road off FS Road 4581.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/02/2017 |
Decision | 08/2017 (Estimated) |
Implementation | 04/2017 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (5), 36 Cfr 220.6(D)(5)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Huron Shores Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management; Watershed Management; Special Use Management
Project Activity:
Developed Site Management; Watershed Improvements
Current Status:
Completed
Project Decision Information
Categorical Exclusion Without Written Decision
Decision Decided Date: 08/17/2017
Forests:
Huron-Manistee National Forest
Districts:
Huron Shores Ranger District
States:
Michigan
Counties:
Iosco
Legal Land Description:
SE , SE , NW , Section 31, T24N, R9E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Randy Griffith
5761 N. Skeel Rd
Oscoda, MI 48750
208-542-5812
rsgriffith@fs.fed.us