East Branch Ontonagon River Restoration Project
This project proposes to restore stream connectivity in the East Branch of the Ontonagon River within the Ottawa National Forest by removing Lower Dam and restoring the river to pre-impoundment conditions.
Project Summary
Current Status:
Completed
Location Summary:
The project is located on the East Branch Ontonagon River in Houghton County, Michigan.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/29/2018 |
| Comment Period | 08/21/2020 |
| Decision | 01/2021 (Estimated) |
| Implementation | 05/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Ottawa National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management
Project Activity:
Watershed Improvements
Project Decision Information
East Branch Ontonagon River Restoration Project
Decision Signed Date: 01/04/2021
Forests:
Ottawa National Forest
Districts:
Kenton Ranger District
States:
Michigan
Counties:
Houghton
Legal Land Description:
Houghton County, Michigan: T47N R36W Sec 22-23
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Christopher Kovala
E6248 US 2
Ironwood, MI 49938
906-852-3500
christopherskovala@fs.fed.us
Last Updated: 3/31/2021