Upper Dam Removal and Restoration
Upper dam is located on the East Branch Ontonagon River. Upper dam consists of old timber, metal pipes, as well as tree material placed by beavers. This project proposes to remove the dam to restore the area to natural conditions and allow for
Project Summary
Location Summary:
Kenton Ranger District
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/01/2023 |
Decision | 02/2025 (Estimated) |
Implementation | 05/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Kenton Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management
Project Activity:
Watershed Improvements
Current Status:
In Progress
Forests:
Ottawa National Forest
Districts:
Kenton Ranger District
States:
Michigan
Counties:
Houghton
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ryan Beatty
4810 E. M28
Kenton, MI 49967
906-285-6897
Ryan.Beatty@usda.gov
Last Updated: 12/26/2024