Keewaydin (Pulsar) Seismic Proposal Lines 2503, 2504, 2505 and 3D Exploration
Keewaydin Resource, Inc. submitted Special Uses Permit (SUP) proposals seeking access over National Forest System (NFS) lands to conduct indirect geophysical exploration on three 2D lines. The 3D project is now cancelled.
Project Summary
Current Status:
Completed
Location Summary:
The project area for the 2D Lines 2503, 2504, 2505 are located on the Kawishiwi Ranger District. Access will occur via overland tracks during frozen conditions. The 3D project has been cancelled.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 08/28/2025 |
| Decision | 10/2025 (Estimated) |
| Implementation | 02/2026 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Kawishiwi Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Keewaydin (Pulsar) Seismic Proposal Lines 2503, 2504, and 2505
Decision Signed Date: 10/20/2025
Forests:
Superior National Forest
Districts:
Kawishiwi Ranger District
States:
Minnesota
Counties:
St. Louis
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Trevor Peck
1393 Highway 169
Ely, MN 55731
801-823-5138