Lima Green
This project proposes to enhance moose habitat, restore red & white pine, enhance the scenic quality along the Gunflint Trail & improve forest conditions through vegetation management, harvests and planting. Temporary roads would be used for access.
Project Summary
Location Summary:
T63N R1W, 1E & 2E and T64N R1W, 1E & 2E.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/11/2011 |
Comment Period | 03/31/2012 |
Decision | 07/2012 (Estimated) |
Implementation | 08/2012 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Gunflint Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Forest Products; Watershed Management; Fuels Management; Road Management; Vegetation Management (Other Than Forest Products); Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements; Species Population Enhancements; Timber Sales (Salvage); Timber Sales (Green); Watershed Improvements
Current Status:
Completed
Project Decision Information
Lima Green Project
Decision Signed Date: 07/12/2012
Legal Notice Date: 07/14/2012
Forests:
Superior National Forest
Districts:
Gunflint Ranger District
States:
Minnesota
Counties:
Cook; Lake
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Rebecca Bartol
2020 W. Highway 61
Grand Marais, MN 55604
218-387-3207
rbartol@fs.fed.us
Last Updated: 7/23/2012