Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/06/2020 |
| Decision | 05/2020 (Estimated) |
| Implementation | 06/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Superior National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Maintenance; Road Improvements/Construction
Current Status:
Completed
Project Decision Information
St. Louis County CSAH #21 Temporary Bridge Construction
Decision Signed Date: 05/28/2020
Forests:
Superior National Forest
Districts:
Kawishiwi Ranger District
States:
Minnesota
Counties:
St. Louis
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Barbara Thompson
8901 Grand Ave Place
Duluth, MN 55808
218-365-7600
bthompson@fs.fed.us
Last Updated: 6/26/2020