Chugach Electric Assoc Relocation of Existing Hope Distribution Line in sec. 3, MP 5.5-5.8, Hope Hwy
The new alignment will require clearing a new 40-foot wide right-of-way along the west side of the Hope Highway and the installation of approximately 1500` of new overhead primary single-phase electric distribution line and retiring the existing line
Project Summary
Location Summary:
Mile post 5.5-5.8, Hope Highway
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 09/26/2013 |
Comment Period | 11/05/2013 |
Decision | 02/2014 (Estimated) |
Implementation | 02/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Seward Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Chugach Electric Association Section 3 Hope Feeder Electric Line Rebuild
Decision Signed Date: 02/06/2014
Legal Notice Date: 02/09/2014
Forests:
Chugach National Forest
Districts:
Seward Ranger District
States:
Alaska
Counties:
Kenai Peninsula
Legal Land Description:
Section 22, T9N, R1W, Seward Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Katherine Van Massenhove
334 4th Avenue
Seward, AK 99664
907-743-9542
kvanmassenhove@fs.fed.us
Last Updated: 2/11/2014